Leith Programme Update
Progress update
All work is currently running on schedule to the programme timescale
Section 6a West (Balfour Street southwards):
· All kerbs re-laid south of Balfour Street
· 75% of existing slabs removed
· 25% of new slabs re-laid
Section 6a East (Jameson Place southwards)
· 50% of existing slabs removed
· 15% new slabs re-laid
· Trial hole to relocate lighting column completed
Section 8a West (Jane Street southwards)
· 40% of existing slabs removed
· New gully connection complete
· Installation of kerbs 50% complete
· 20% of new slabs re-laid
Section 8a East (South of Manderston Street)
· 50% of existing slabs removed
· Installation of kerbs 75% complete
· 15% of new slabs re-laid
Other sections:
· Snagging works to sections 5 and 7 on-going
Looking ahead for next week:
· Continue with footpath works in all sections
· Relocate lighting columns in sections 6 and 8
· Gully installation at Stead’s Place